Phase two of the Yeovil site expansion project is now well underway.
After some delays with the groundworks, the steel work was delivered and erected in a matter of days, with the first of the bin cones following the same day.
The crane has since departed to allow for six days of welding to commence in order to fix the cones and the first row of bin panels.
Then a 280 further bin panels will be lifted and bolted into place. Fingers crossed for some dry weather!